Click on the links to the left to see some pictures. These show the progress of the work throughout the renovation period. Below is a rough timeline of the project:

  • We first viewed the house in October 2005, you can see the condition of it when we were there
  • The purchase went through in early December 2005 and work started shortly afterwards
  • Towards the end of January 2006 Bryastovets experienced one of their worst winters for many years, work was stopped for almost a month
  • During February 2006 we recieved photos from the builders
  • Early in May 2006 Neil went out to inspect the works. By then the side building was clearly starting to look more like a house
  • In late May/early June Ian went out for a visit